Roads
and Bridges |
| |
Before
Nationalization
Dejen – Bichena - Motta Road Project
The Project consisted of a 146km road connecting the town
of Dejen to Motta, passing through the town of Bichena, in
Gojam province. The project is an alternative route connecting
Dejen to Bahir Dar, through Motta which reduces the route
by certain kilo meters and give access road to the surrounding
rural people. The project was financed by the International
Development Agency (IDA). It was successfully completed on
schedule in 1980 at a cost of Birr 21.0 million at the time
under the supervision of DCI/TAMS a consulting company of
USA.
Jimma
- Chida Road Project
This road connects the town of Jimma to the town of Chida
and is 82.5 km long located in South Western part of Ethiopia.
The construction of this project was started in 1979, and
was successfully completed on schedule in 1982. The project
was financed by the Government of Ethiopia and the African
Development Bank. The cost was Birr 23.0 million. The supervising
engineer of the project, Dr. Engineer Walter GMBH & KG
Intl. was from the Federal Republic of Germany.
After The Company's Return To The Owners
Dawnt - Lalibela RR50 Project
The Dawnt - Lalibela Rural Road is 120km in
length and extends from the village called Dawnt to the historical
town of Lalibela. The terrain along the route was 60% mountainous
and 40% rolling and sliding landscape.
The
reinforced concrete bridge over the Kechin Abeba River consists
of Y-framed pre-fab concrete girders This method of bridge
construction is the first of its kind in the country and
BERTA is proud of introducing the system to the local industry
and to successfully withstand the demands posed by the introduction
of such an engineering challenge.
BERTA
undertook the Dawnt-Lalibela RR50 Project as a Turn-key
contract which includes both the design and the construction
of the road. The supervision of the project was carried
out by Roughton International of UK at the initial stage
(1993 -1998) and then by United Consulting Engineers (UNICONE)
at the final stage (1998 – 2001). The
overall project cost was Birr 72.159 million.
Major Workes Executed At Dawnt - Lalibela RR50 project
|
|
| Description |
Unit |
|
Actual
Work |
|
| Slab
Cuvert |
No. |
|
33 |
|
| Pipe
Culvert |
No. |
|
238 |
|
|
| |
|
|
|
| |
|
|
 |